The timeline below includes our anticipated timescales for the proposed development at Bennerley, from the close of this public engagement process to completion of the proposed scheme.

18th July 2025

Close of public engagement

July August 2025

Project team to review responses received to the public engagement process, and consider necessary amendments to the proposals prior to submission of the planning application

September 2025

Anticipated submission of an outline planning application to Broxtowe Borough Council. Once the planning application has been received and validated by the Borough Council, there will be further opportunity to make comments direct to the Council as part of the planning application process

September 2026

Anticipated determination of the outline planning application by Broxtowe Borough Council

subject to approval of outline planning application...
2030
Anticipated completion of development
2027
Commencement on site